MAN Production Hall 1, 2009

Warehouse A35 and Trailer Yard Canopy

An additional warehouse for mechanical production was to be built at the MAN site in Munich’s Allach district. This extension to production hall 1 was to provide 4,029m2 of usable an area.

To the east of production hall 1, a canopy for the completed trailers was to have been built. This canopy was designed as a filigree steel structure reminiscent of two outstretched wings.

Both projects were initiated under a general planning framework agreement but were not subsequently carried out.

Category

Industry

Location

Munich
Project Location Munich

Typology

General Planning

Status

Not completed

Timeline

2008–2009

Gross floor area

11.500 m²

Service phases

1, 2, 3, 4

Client

MAN Nutzfahrzeuge AG

abh-munich-MAN-fertigungshalle-1

abh-munich-MAN-fertigungshalle-1

abh-munich-MAN-fertigungshalle-1

abh-munich-MAN-fertigungshalle-1

Category

Industry

Location

Munich
Project Location Munich

Typology

General Planning

Status

Not completed

Timeline

2008–2009

Gross floor area

11.500 m²

Service phases

1, 2, 3, 4

Client

MAN Nutzfahrzeuge AG